Flushing City Council

Minutes

July 5, 2005

 

 

A Special Meeting of the Flushing City Council was called to order on Tuesday, July 5, 2005 at 4:00 p.m. by Mayor Janice L. Gensel, followed by the Pledge of Allegiance to the Flag and invocation.

 

Present:                                  Richard L. Bade

John C. Gault

                                                Janice L. Gensel

                                                George G. Kozan

                                                Richard Mark

                                                Teresa K. Salem

                                                Michael T. Szukhent

 

Absent:                                   None

                                   

Others Present:                      Dennis J. Bow, City Manager

                                                Nancy G. Parks, City Clerk/Treasurer

                                                Edward G. Henneke, City Attorney

 

MEETING OPEN TO THE PUBLIC:

 

No comments.

 

REPORTS:

 

City Hall/Police Station Construction Status – The City Attorney brought the Council up to date on the status of the negotiations with the Hanover Insurance Company.  The City Manager stated that many of the previous subcontractors have been paid and that some are waiting to sign contracts with the new contractor.  Hanover hired a representative from Chicago and he came in and gathered information to put together a new bid spec.  The contractor that has been selected is Siwek.  Siwek put together a proposal and Hanover has agreed to pay the amount over and above what the City has in the bank to complete the project.  Additional costs that the City has incurred for utility bills, attorney fees, site clean up and police services, will be paid by Hanover.   The City is in dispute with Hanover over two (2) items:  1) the elevator, because it was left outside, and alleged over-payment on the brickwork ($31,425.00), and 2) additional architectural fees ($35,112.87).  The architectural fees include $12,000.00 in future costs to complete the project.

 

 

 

 

 

 

 

Flushing City Council

Minutes

July 5, 2005

 

Page Two

 

 

            The attorney stated that Hanover has exercised option 4.3 under the performance bond.  Hanover has agreed to pay to the City the amount of damages as described in Paragraph 6 in excess of the Balance of the Contract Price incurred by the City resulting from Direct Building’s default.  The new contractor, Siwek, will be required to provide their own performance bond.  Hanover is requesting the City sign a release.  The City attorney doesn’t believe that the performance bond requires a release.  The performance bond covers any latent defects that may result from Direct Building’s construction.  Mr. Henneke also stated that, through Hanover’s attorney, they have agreed to make a partial payment on the architect fees that have accrued; much of the work done was at the request of Hanover.  Hanover has also agreed to pay all subcontractors that were part of the original contract.  The amount in question, relating to the elevator and brickwork, will be settled through arbitration.

 

            Several Councilpersons questioned why the City should be liable for even one penny, when the City hired a contractor who was bonded.  Councilperson Gault feels that the City should pursue this matter in court.  Mr. Henneke explained that the City had a separate contract with THA; the architects did not have a contract with Direct Building.  Mr. Henneke stated that the City could contract directly with Siwek and go to court with Hanover.

 

            The City Manager stated that the City has some options:  1) the City could contract with Siwek and sue Hanover for breach of contract, or 2) if this is Hanover’s last and final offer, the City can wait until the outstanding issues are resolved.

 

            Councilperson Salem questioned the problem with the elevator.  The City Manager responded that it is Hanover’s contention that THA allowed the elevator to stay out in the weather longer than it should have, thus nullifying the warranty.  There may be absolutely nothing wrong with the elevator.  Hanover claims that THA should have backed the cost of the elevator out of a future payment.  Councilperson Mark stated that the architect does not control the job site and should not be held responsible.

 

            Mr. Henneke suggested that Council work to resolve these issues so that the project could move forward and not be tied up in court.  Councilperson Mark brought up the concern of latent defects and how Hanover and Siwek’s bonding company could dispute which company is responsible for latent defects.  Councilperson Szukhent asked if we could require Hanover to bond Siwek.  Mr. Henneke responded that, under this performance bond, the City could not.  Councilperson Szukhent felt that the City should attempt to negotiate this.

 

Flushing City Council

Minutes

July 5, 2005

 

Page Three

 

 

Agreement – Motion by Mark, seconded by Bade, to direct the City Attorney to prepare a counter offer to Hanover’s proposal to include the following:  1) Hanover issue a performance bond to Siwek to avoid the issue of latent defects, 2) Hanover be responsible for architect fees, 3) that compensation include the cost of a new elevator or a guarantee that the elevator is under complete warranty, and 4) that Hanover provide for all additional attorney fees.

 

            Yea:     Bade, Gault, Kozan, Mark, Salem, Szukhent, Gensel

            Nay:     None

            Motion Carried.

 

Adjournment – Motion by Kozan, seconded by Bade, to adjourn.

 

            Yea:     Bade, Gault, Kozan, Mark, Salem, Szukhent, Gensel

            Nay:     None

            Motion Carried.

 

Adjourn:                      5:50 p.m.

 

 

 

_____________________________                         ______________________________

Janice L. Gensel, Mayor                                              Nancy G. Parks, City Clerk/Treasurer